Ministry of New and Renewable Energy issued guidelines for transparent bidding process for implementation of Scheme for setting up of 1000 MW Wind Power Project connected to inter-state transmission system (ISTS).

As per guidelines, the Wind Power Projects will be selected through open and transparent competitive bidding followed by e-reverse auction and the capacity may go higher than 1000 MW, if there is demand from Buying Entities.

PTC India Ltd will sign Power Purchase Agreement (PPA) with wind projects at bidded tariff and back-to-back Power Sale Agreement (PSA) with Buying Entities at a pooled price of the total bids selected. The term of PPA and PSA will be 25 years.

The bidder can bid for a minimum capacity of 50 MW and maximum up to 250 MW. The selected bidder is required to injected wind power at ISTS interconnection point. Bidder is allowed to install 5% of additional rated capacity that will compensate auxiliary consumption and system losses up to interconnection point.